By August 31 2006
– Grant was given in mid february
– Content Map creation was started in March and ended in end June.
– Shipa Sayura Software System prototype developed and reviewed internally in mid june.
– Shilpa Sayura Conten Map Reviewed by Teahers Group during June/July
– Content Map Approved in mid August.
– Content Creation Started in mid August. How ever at least 20% of the content had been created before the project was available for subjects Sinhala, Social Science and Envoronment
Future Plans
Shilpa Sayura aims to create at least 60% of the content core during the pilot stage. The implementation to be started in December 2007.
» login or register to post comments
– Grant was given in mid february
– Content Map creation was started in March and ended in end June.
– Shipa Sayura Software System prototype developed and reviewed internally in mid june.
– Shilpa Sayura Conten Map Reviewed by Teahers Group during June/July
– Content Map Approved in mid August.
– Content Creation Started in mid August. How ever at least 20% of the content had been created before the project was available for subjects Sinhala, Social Science and Envoronment
Future Plans
Shilpa Sayura aims to create at least 60% of the content core during the pilot stage. The implementation to be started in December 2007.